Ditch Creek — Project Summary

Queue ID
NYISO-C24-319
Capacity
199.5 MW
Technology
Solar+Battery
Status
active
Location
Madison, NY
Region
NYISO
Developer
Ditch Creek Solar LLC
IA Status

Ditch Creek

BetaActiveSolarBatteryNYISOLBNL

199.5 MW hybrid in Madison, NY · In queue since October 2024 · Proposed COD December 2027

199.5 MW

Capacity

1

Components

Solar

1y 5m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 2m

Pre-Study0%
Queue EntryOct 5, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

NY

County

Madison

Region

NYISO

Developer

Ditch Creek Solar LLC

Utility

NYPA

Entity

NYISO

Point of Interconnection

CLAY to EDIC 345 kV Line #15 Circuit #2

Data Source

LBNL

No news available for this project.