DOVER NY BESS
BetaActiveBatteryNYISOLBNL
1,000 MW storage in Dutchess, NY · In queue since October 2024 · Proposed COD September 2028
1,000 MW
Capacity
1
Components
Battery
1y 5m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntryOct 3, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-01
Project Details
State
NY
County
Dutchess
Region
NYISO
Developer
DOVER PLAINS ENERGY PROPERTIES LLC
Utility
ConEd
Entity
NYISO
Point of Interconnection
Pleasant Valley-Cricket Valley 345kV
Data Source
LBNL
No news available for this project.