DOVER NY BESS — Project Summary

Queue ID
NYISO-C24-316
Capacity
1000 MW
Technology
Battery
Status
active
Location
Dutchess, NY
Region
NYISO
Developer
DOVER PLAINS ENERGY PROPERTIES LLC
IA Status

DOVER NY BESS

BetaActiveBatteryNYISOLBNL

1,000 MW storage in Dutchess, NY · In queue since October 2024 · Proposed COD September 2028

1,000 MW

Capacity

1

Components

Battery

1y 5m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 11m

Pre-Study0%
Queue EntryOct 3, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-01

Project Details

State

NY

County

Dutchess

Region

NYISO

Developer

DOVER PLAINS ENERGY PROPERTIES LLC

Utility

ConEd

Entity

NYISO

Point of Interconnection

Pleasant Valley-Cricket Valley 345kV

Data Source

LBNL

No news available for this project.