Southport Solar PV Project — Project Summary

Queue ID
NYISO-C24-313
Capacity
42 MW
Technology
Solar
Status
active
Location
Chemung, NY
Region
NYISO
Developer
NY Power Authority
IA Status

Southport Solar PV Project

BetaActiveSolarNYISOLBNL

42 MW generation in Chemung, NY · In queue since October 2024 · Proposed COD November 2028

42 MW

Capacity

1

Components

Solar

1y 5m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 1m

Pre-Study0%
Queue EntryOct 2, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-01

Project Details

State

NY

County

Chemung

Region

NYISO

Developer

NY Power Authority

Utility

NYSEG

Entity

NYISO

Point of Interconnection

Caton Ave. 115 kV Station

Data Source

LBNL

No news available for this project.