Southport Solar PV Project
BetaActiveSolarNYISOLBNL
42 MW generation in Chemung, NY · In queue since October 2024 · Proposed COD November 2028
42 MW
Capacity
1
Components
Solar
1y 5m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 1m
Pre-Study0%
Queue EntryOct 2, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-01
Project Details
State
NY
County
Chemung
Region
NYISO
Developer
NY Power Authority
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Caton Ave. 115 kV Station
Data Source
LBNL