St. Regis
BetaActiveSolarBatteryNYISOLBNL
58.5 MW hybrid in St. Lawrence, NY · In queue since October 2024 · Proposed COD May 2028
58.5 MW
Capacity
1
Components
Solar
1y 5m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 7m
Pre-Study0%
Queue EntryOct 2, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-01
Project Details
State
NY
County
St. Lawrence
Region
NYISO
Developer
BW Solar Holding Inc.
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Dennison-Colton #5 115kV Line.
Data Source
LBNL
No news available for this project.