Black Cherry BESS
BetaActiveBatteryNYISOLBNL
400 MW storage in Mckean, PA · In queue since October 2024 · Proposed COD February 2027
400 MW
Capacity
1
Components
Battery
1y 5m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 4m
Pre-Study0%
Queue EntryOct 1, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-02-01
Project Details
State
PA
County
Mckean
Region
NYISO
Developer
Black Cherry Wind Power, LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Homer City to Piercebrook 345kV Line
Data Source
LBNL
No news available for this project.