NY Chateaugay 0 Willis Rd Storage
BetaActiveBatteryNYISOLBNL + Live
150 MW storage in Franklin, NY · In queue since October 2024 · Proposed COD April 2028
150 MW
Capacity
1
Components
Battery
1y 5m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 6m
Pre-Study0%
Queue EntryOct 1, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-01
Project Details
State
NY
County
Franklin
Region
NYISO
Developer
Chateauguay River, LLC
Utility
NYPA
Entity
NYISO
Point of Interconnection
Willis 230kV substation
Data Source
LBNL + Live