Kimberlite Solar — Project Summary

Queue ID
NYISO-C24-300
Capacity
175 MW
Technology
Solar
Status
active
Location
Clearfield, PA
Region
NYISO
Developer
Kimberlite Solar Power, LLC
IA Status

Kimberlite Solar

BetaActiveSolarNYISOLBNL + Live

175 MW generation in Clearfield, PA · In queue since September 2024 · Proposed COD March 2029

175 MW

Capacity

1

Components

Solar

1y 6m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

4y 6m

Pre-Study0%
Queue EntrySep 30, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-03-01

Project Details

State

PA

County

Clearfield

Region

NYISO

Developer

Kimberlite Solar Power, LLC

Utility

NYSEG

Entity

NYISO

Point of Interconnection

Homer City - Mainesburg 345kV Line (L47)

Data Source

LBNL + Live