Birch-Whistler
BetaActiveWindNYISOLBNL
100 MW generation in Delaware, NY · In queue since September 2024 · Proposed COD December 2030
100 MW
Capacity
1
Components
Wind
1y 6m
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
6y 3m
Pre-Study0%
Queue EntrySep 27, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-12-01
Project Details
State
NY
County
Delaware
Region
NYISO
Developer
Birch Whistler, LLC
Utility
NYPA
Entity
NYISO
Point of Interconnection
Line Tap Edic to Fraser Line, 345kV
Data Source
LBNL
No news available for this project.