Oswego Clean Energy
BetaActiveSolarNYISOLBNL + Live
24.9 MW generation in Oswego, NY · In queue since September 2024 · Proposed COD December 2026
24.9 MW
Capacity
1
Components
Solar
1y 6m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 3m
Pre-Study0%
Queue EntrySep 27, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
NY
County
Oswego
Region
NYISO
Developer
Oswego Clean Energy Holdings
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Oswego 115 kV Substation
Data Source
LBNL + Live