Harrigan Solar
BetaActiveSolarNYISOLBNL
100 MW generation in Franklin, NY · In queue since September 2024 · Proposed COD March 2030
100 MW
Capacity
1
Components
Solar
1y 6m
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
5y 6m
Pre-Study0%
Queue EntrySep 26, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-03-01
Project Details
State
NY
County
Franklin
Region
NYISO
Developer
ACE DevCo NC,LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Willis to Lyon Mountain Line Tap 115 kV
Data Source
LBNL