Brentwood Energy Storage
BetaActiveBatteryNYISOLBNL + Live
49.1 MW storage in Suffolk, NY · In queue since September 2024 · Proposed COD August 2028
49.1 MW
Capacity
1
Components
Battery
1y 6m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntrySep 25, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-08-01
Project Details
State
NY
County
Suffolk
Region
NYISO
Developer
the NY Power Authority
Utility
LIPA
Entity
NYISO
Point of Interconnection
Brentwood 69 kV Substation
Data Source
LBNL + Live
No news available for this project.