Eastern Solar PV Project — Project Summary

Queue ID
NYISO-C24-279
Capacity
30 MW
Technology
Solar
Status
active
Location
Ulster, NY
Region
NYISO
Developer
NY Power Authority
IA Status

Eastern Solar PV Project

BetaActiveSolarNYISOLBNL

30 MW generation in Ulster, NY · In queue since September 2024 · Proposed COD November 2028

30 MW

Capacity

1

Components

Solar

1y 6m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 2m

Pre-Study0%
Queue EntrySep 24, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-01

Project Details

State

NY

County

Ulster

Region

NYISO

Developer

NY Power Authority

Utility

CHGE

Entity

NYISO

Point of Interconnection

Kerhonkson to Honks Falls 69kV line

Data Source

LBNL