Sullivan-Woodbourne Solar Project — Project Summary

Queue ID
NYISO-C24-278
Capacity
100 MW
Technology
Solar
Status
active
Location
Sullivan, NY
Region
NYISO
Developer
NY Power Authority
IA Status

Sullivan-Woodbourne Solar Project

BetaActiveSolarNYISOLBNL

100 MW generation in Sullivan, NY · In queue since September 2024 · Proposed COD November 2028

100 MW

Capacity

1

Components

Solar

1y 6m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 2m

Pre-Study0%
Queue EntrySep 24, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-01

Project Details

State

NY

County

Sullivan

Region

NYISO

Developer

NY Power Authority

Utility

NYSEG

Entity

NYISO

Point of Interconnection

Mountaindale - Woodbourne 115 kV line

Data Source

LBNL

No news available for this project.