Stonewall Solar — Project Summary

Queue ID
NYISO-C24-269
Capacity
145 MW
Technology
Solar+Battery
Status
active
Location
Delaware, NY
Region
NYISO
Developer
Stonewall Solar LLC
IA Status

Stonewall Solar

BetaActiveSolarBatteryNYISOLBNL

145 MW hybrid in Delaware, NY · In queue since September 2024 · Proposed COD May 2028

145 MW

Capacity

1

Components

Solar

1y 6m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 8m

Pre-Study0%
Queue EntrySep 24, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-01

Project Details

State

NY

County

Delaware

Region

NYISO

Developer

Stonewall Solar LLC

Utility

NYSEG

Entity

NYISO

Point of Interconnection

Fraser Tap-Colliers 115 kV line #951

Data Source

LBNL

No news available for this project.