West Laurens — Project Summary

Queue ID
NYISO-C24-260
Capacity
350 MW
Technology
Solar
Status
active
Location
Otsego, NY
Region
NYISO
Developer
ACE DevCo NC, LLC
IA Status

West Laurens

BetaActiveSolarNYISOLBNL

350 MW generation in Otsego, NY · In queue since September 2024 · Proposed COD December 2029

350 MW

Capacity

1

Components

Solar

1y 6m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 3m

Pre-Study0%
Queue EntrySep 23, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-01

Project Details

State

NY

County

Otsego

Region

NYISO

Developer

ACE DevCo NC, LLC

Utility

NYPA

Entity

NYISO

Point of Interconnection

Marcy to Coopers Corner - 345 kV

Data Source

LBNL