Block Perch solar — Project Summary

Queue ID
NYISO-C24-246
Capacity
85 MW
Technology
Solar
Status
active
Location
Chautauqua, NY
Region
NYISO
Developer
ACE DevCo NC LLC
IA Status

Block Perch solar

BetaActiveSolarNYISOLBNL

85 MW generation in Chautauqua, NY · In queue since September 2024 · Proposed COD November 2029

85 MW

Capacity

1

Components

Solar

1y 6m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 2m

Pre-Study0%
Queue EntrySep 23, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-11-01

Project Details

State

NY

County

Chautauqua

Region

NYISO

Developer

ACE DevCo NC LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Moon Road-Falconer Line 175 115V

Data Source

LBNL

No news available for this project.