Buttercup Wind
BetaActiveWindNYISOLBNL + Live
49.9 MW generation in Chautauqua, NY · In queue since September 2024 · Proposed COD December 2029
49.9 MW
Capacity
1
Components
Wind
1y 6m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 3m
Pre-Study0%
Queue EntrySep 21, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-01
Project Details
State
NY
County
Chautauqua
Region
NYISO
Developer
Buttercup Wind LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Dunkirk-Falconer Line 160 115kV
Data Source
LBNL + Live
No news available for this project.