South Dow (Lucy's Energy Reserve) — Project Summary

Queue ID
NYISO-C24-226
Capacity
175 MW
Technology
Battery
Status
active
Location
Chautauqua, NY
Region
NYISO
Developer
Lucy?s Energy Reserve LLC
IA Status

South Dow (Lucy's Energy Reserve)

BetaActiveBatteryNYISOLBNL

175 MW storage in Chautauqua, NY · In queue since September 2024 · Proposed COD May 2028

175 MW

Capacity

1

Components

Battery

1y 6m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 8m

Pre-Study0%
Queue EntrySep 20, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-01

Project Details

State

NY

County

Chautauqua

Region

NYISO

Developer

Lucy?s Energy Reserve LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Falconer 115kV Substation

Data Source

LBNL