Cohocton — Project Summary

Queue ID
NYISO-C24-224
Capacity
130 MW
Technology
Solar+Battery
Status
active
Location
Steuben, NY
Region
NYISO
Developer
ACE DevCo NC, LLC
IA Status

Cohocton

BetaActiveSolarBatteryNYISOLBNL + Live

130 MW hybrid in Steuben, NY · In queue since September 2024 · Proposed COD October 2029

130 MW

Capacity

1

Components

Solar

1y 6m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 1m

Pre-Study0%
Queue EntrySep 20, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-10-01

Project Details

State

NY

County

Steuben

Region

NYISO

Developer

ACE DevCo NC, LLC

Utility

NYSEG

Entity

NYISO

Point of Interconnection

Tap 115kV line from Bath 115 kV station to Spencer Hill (Howard) 115 kV Station

Data Source

LBNL + Live