Blue Mountain BESS
BetaActiveBatteryNYISOLBNL
100 MW storage in Ulster, NY · In queue since September 2024 · Proposed COD December 2028
100 MW
Capacity
1
Components
Battery
1y 6m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 3m
Pre-Study0%
Queue EntrySep 20, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
NY
County
Ulster
Region
NYISO
Developer
ACE DevCo NC, LLC
Utility
CHGE
Entity
NYISO
Point of Interconnection
Saugerties to Hurley 69 kV Line
Data Source
LBNL
No news available for this project.