Krenzer — Project Summary

Queue ID
NYISO-C24-219
Capacity
150 MW
Technology
Solar
Status
active
Location
Monroe, NY
Region
NYISO
Developer
ACE DevCo NC, LLC
IA Status

Krenzer

BetaActiveSolarNYISOLBNL

150 MW generation in Monroe, NY · In queue since September 2024 · Proposed COD March 2030

150 MW

Capacity

1

Components

Solar

1y 6m

In Queue

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

5y 6m

Pre-Study0%
Queue EntrySep 20, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-03-01

Project Details

State

NY

County

Monroe

Region

NYISO

Developer

ACE DevCo NC, LLC

Utility

RG&E

Entity

NYISO

Point of Interconnection

Station 128 to Station 82 115 kV

Data Source

LBNL

No news available for this project.