Marcy BESS 2 — Project Summary

Queue ID
NYISO-C24-211
Capacity
195 MW
Technology
Battery
Status
active
Location
Oneida, NY
Region
NYISO
Developer
The Commodore Storage, LLC
IA Status

Marcy BESS 2

BetaActiveBatteryNYISOLBNL

195 MW storage in Oneida, NY · In queue since September 2024 · Proposed COD January 2029

195 MW

Capacity

1

Components

Battery

1y 6m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

4y 4m

Pre-Study0%
Queue EntrySep 20, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-01-01

Project Details

State

NY

County

Oneida

Region

NYISO

Developer

The Commodore Storage, LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Volney - Marcy 345 kV

Data Source

LBNL

No news available for this project.