Independence BESS
BetaActiveBatteryNYISOLBNL
200 MW storage in Oswego, NY · In queue since September 2024 · Proposed COD June 2028
200 MW
Capacity
1
Components
Battery
1y 6m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 9m
Pre-Study0%
Queue EntrySep 19, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-01
Project Details
State
NY
County
Oswego
Region
NYISO
Developer
Independence BESS LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Independence 345 KV
Data Source
LBNL
No news available for this project.