Trelina Energy Storage
BetaActiveBatteryNYISOLBNL + Live
120 MW storage in Seneca, NY · In queue since September 2024 · Proposed COD December 2029
120 MW
Capacity
1
Components
Battery
1y 6m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 3m
Pre-Study0%
Queue EntrySep 19, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-01
Project Details
State
NY
County
Seneca
Region
NYISO
Developer
NextEra Energy Resources Interconnection Holdings, LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Planned Q720 Trelina Solar Switchyard on Border City to Station 168 115 kV line