Queue ID
NYISO-C24-179
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Tompkins, NY
Region
NYISO
Developer
Silverline Energy Center, LLC
IA Status

Silverline Energy Center

BetaActiveSolarBatteryNYISOLBNL

150 MW hybrid in Tompkins, NY · In queue since September 2024 · Proposed COD December 2029

150 MW

Capacity

1

Components

Solar

1y 6m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 3m

Pre-Study0%
Queue EntrySep 17, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-01

Project Details

State

NY

County

Tompkins

Region

NYISO

Developer

Silverline Energy Center, LLC

Utility

NYSEG

Entity

NYISO

Point of Interconnection

Miliken to Etna Line #974 115 kV line

Data Source

LBNL