Long Island Wind
1,310 MW generation in Suffolk, NY · In queue since September 2024 · Proposed COD December 2033
1,310 MW
Capacity
1
Components
Offshore Wind
1y 6m
In Queue
—
IA Status
COD target: 2033
Total Duration
9y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2033-12-01
State
NY
County
Suffolk
Region
NYISO
Developer
Bay State Wind
Utility
NYPA
Entity
NYISO
Point of Interconnection
Ruland Road 345kV
Data Source
LBNL
Sunrise Wind Can Resume Work After Court Ruling
A federal judge has allowed offshore work to resume at Sunrise Wind's offshore wind farm about 30 miles off the coast of Montauk, the fifth of five projects...
Wind Farms Challenge Federal Stop on Offshore Work
The developers of the Revolution Wind wind farm off the coast of Rhode Island and Empire Wind off the coast of Long Beach, Long Island,...
Wind Farms Challenge Federal Stop on Offshore Work
The developers of the Revolution Wind wind farm off the coast of Rhode Island and Empire Wind off the coast of Long Beach, Long Island,...
Long Island Wind Farms Respond to Federal Suspension
Two of the five offshore wind farms whose leases were paused by the Trump administration on Monday are designed to power Long Island's electric grid,...
Last updated 2026-03-26