KCE NY 34 — Project Summary

Queue ID
NYISO-C24-173
Capacity
100 MW
Technology
Battery
Status
active
Location
Ulster, NY
Region
NYISO
Developer
KCE NY 34, LLC
IA Status

KCE NY 34

BetaActiveBatteryNYISOLBNL + Live

100 MW storage in Ulster, NY · In queue since September 2024 · Proposed COD December 2028

100 MW

Capacity

1

Components

Battery

1y 6m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 3m

Pre-Study0%
Queue EntrySep 17, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

NY

County

Ulster

Region

NYISO

Developer

KCE NY 34, LLC

Utility

CHGE

Entity

NYISO

Point of Interconnection

Saugerties 69 kV

Data Source

LBNL + Live

No news available for this project.