BRESH HYBRID — Project Summary

Queue ID
NYISO-C24-172
Capacity
59.2 MW
Technology
Solar+Battery
Status
active
Location
Ulster, NY
Region
NYISO
Developer
Blue Stone Renewable XVI
IA Status

BRESH HYBRID

BetaActiveSolarBatteryNYISOLBNL

59.2 MW hybrid in Ulster, NY · In queue since September 2024 · Proposed COD December 2027

59.2 MW

Capacity

1

Components

Solar

1y 6m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 3m

Pre-Study0%
Queue EntrySep 17, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

NY

County

Ulster

Region

NYISO

Developer

Blue Stone Renewable XVI

Utility

CHGE

Entity

NYISO

Point of Interconnection

BOULEVARD 69 kV SUBSTATION

Data Source

LBNL