Zenith BESS — Project Summary

Queue ID
NYISO-C24-170
Capacity
165 MW
Technology
Battery
Status
active
Location
Onondaga, NY
Region
NYISO
Developer
Zenith Power LLC
IA Status

Zenith BESS

BetaActiveBatteryNYISOLBNL

165 MW storage in Onondaga, NY · In queue since September 2024 · Proposed COD October 2029

165 MW

Capacity

1

Components

Battery

1y 6m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 1m

Pre-Study0%
Queue EntrySep 17, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-10-01

Project Details

State

NY

County

Onondaga

Region

NYISO

Developer

Zenith Power LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Geres Lock-Tilden Line 16 115kV

Data Source

LBNL

No news available for this project.