Ball Hill BESS — Project Summary

Queue ID
NYISO-C24-168
Capacity
250 MW
Technology
Battery
Status
active
Location
Chautauqua, NY
Region
NYISO
Developer
Northland Power U.S. Projects Inc
IA Status

Ball Hill BESS

BetaActiveBatteryNYISOLBNL

250 MW storage in Chautauqua, NY · In queue since September 2024 · Proposed COD May 2028

250 MW

Capacity

1

Components

Battery

1y 6m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 8m

Pre-Study0%
Queue EntrySep 17, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-01

Project Details

State

NY

County

Chautauqua

Region

NYISO

Developer

Northland Power U.S. Projects Inc

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Stebbins Road 230kV

Data Source

LBNL