KCE NY 38
BetaActiveBatteryNYISOLBNL + Live
250 MW storage in Columbia, NY · In queue since September 2024 · Proposed COD January 2029
250 MW
Capacity
1
Components
Battery
1y 6m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 4m
Pre-Study0%
Queue EntrySep 16, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-01-01
Project Details
State
NY
County
Columbia
Region
NYISO
Developer
KCE NY 38, LLC
Utility
Transco
Entity
NYISO
Point of Interconnection
Churchtown 115 kV Substation
Data Source
LBNL + Live
No news available for this project.