KCE NY 28 — Project Summary

Queue ID
NYISO-C24-164
Capacity
45 MW
Technology
Battery
Status
active
Location
Suffolk, NY
Region
NYISO
Developer
KCE NY 28, LLC
IA Status

KCE NY 28

BetaActiveBatteryNYISOLBNL

45 MW storage in Suffolk, NY · In queue since September 2024 · Proposed COD January 2029

45 MW

Capacity

1

Components

Battery

1y 6m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

4y 4m

Pre-Study0%
Queue EntrySep 16, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-01-01

Project Details

State

NY

County

Suffolk

Region

NYISO

Developer

KCE NY 28, LLC

Utility

LIPA

Entity

NYISO

Point of Interconnection

Riverhead - Tuthill 69kV

Data Source

LBNL