Cruiser BESS — Project Summary

Queue ID
NYISO-C24-159
Capacity
100 MW
Technology
Battery
Status
active
Location
Suffolk, NY
Region
NYISO
Developer
Viridity Energy Solutions
IA Status

Cruiser BESS

BetaActiveBatteryNYISOLBNL

100 MW storage in Suffolk, NY · In queue since September 2024 · Proposed COD March 2028

100 MW

Capacity

1

Components

Battery

1y 6m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 6m

Pre-Study0%
Queue EntrySep 12, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-01

Project Details

State

NY

County

Suffolk

Region

NYISO

Developer

Viridity Energy Solutions

Utility

LIPA

Entity

NYISO

Point of Interconnection

Pulaski 69kV

Data Source

LBNL

No news available for this project.