Fuller Storage
BetaActiveBatteryNYISOLBNL
20 MW storage in Orange, NY · In queue since September 2024 · Proposed COD August 2028
20 MW
Capacity
1
Components
Battery
1y 6m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntrySep 12, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-08-01
Project Details
State
NY
County
Orange
Region
NYISO
Developer
Granada Solar, LLC
Utility
CHGE
Entity
NYISO
Point of Interconnection
East Walden 1115 kV Substation
Data Source
LBNL
No news available for this project.