Grass River Solar
BetaActiveSolarNYISOLBNL
80 MW generation in St. Lawrence, NY · In queue since September 2024 · Proposed COD August 2028
80 MW
Capacity
1
Components
Solar
1y 6m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntrySep 12, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-08-01
Project Details
State
NY
County
St. Lawrence
Region
NYISO
Developer
Granada Solar, LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
N. Ogdensburg - Alcoa 115 kV Line (Line # 13)
Data Source
LBNL
No news available for this project.