Zenobe Stockton LLC
BetaActiveBatteryNYISOLBNL
100 MW storage in Chautauqua, NY · In queue since September 2024 · Proposed COD January 2029
100 MW
Capacity
1
Components
Battery
1y 6m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 4m
Pre-Study0%
Queue EntrySep 12, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-01-01
Project Details
State
NY
County
Chautauqua
Region
NYISO
Developer
Zenobe Stockton LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Moon Road 115kV
Data Source
LBNL