Kingbird Solar
BetaActiveSolarNYISOLBNL
20 MW generation in Chautauqua, NY · In queue since September 2024 · Proposed COD September 2027
20 MW
Capacity
1
Components
Solar
1y 6m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3 years
Pre-Study0%
Queue EntrySep 11, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-01
Project Details
State
NY
County
Chautauqua
Region
NYISO
Developer
Kingbird Solar NY LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Gardenville to Dunkirk 115kV Line - Line #142
Data Source
LBNL
No news available for this project.