River Road Energy Storage — Project Summary

Queue ID
NYISO-C24-134
Capacity
247.5 MW
Technology
Battery
Status
active
Location
Erie, NY
Region
NYISO
Developer
MN8 Energy Development Company LLC
IA Status

River Road Energy Storage

BetaActiveBatteryNYISOLBNL

247.5 MW storage in Erie, NY · In queue since September 2024 · Proposed COD December 2028

247.5 MW

Capacity

1

Components

Battery

1y 6m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 3m

Pre-Study0%
Queue EntrySep 6, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

NY

County

Erie

Region

NYISO

Developer

MN8 Energy Development Company LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Packard-Huntley 230 kV Line#78

Data Source

LBNL

No news available for this project.