Town Line Solar Phase II
BetaActiveSolarBatteryNYISOLBNL + Live
60 MW hybrid in Sullivan, NY · In queue since September 2024 · Proposed COD December 2027
60 MW
Capacity
1
Components
Solar
1y 6m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 3m
Pre-Study0%
Queue EntrySep 5, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
NY
County
Sullivan
Region
NYISO
Developer
RWE Solar Development, LLC
Utility
NYPA
Entity
NYISO
Point of Interconnection
Coopers Corner to Middletown Tap 345 kV Line
Data Source
LBNL + Live
No news available for this project.