Capital Energy Storage
BetaActiveBatteryNYISOLBNL
190 MW storage in Albany, NY · In queue since September 2024 · Proposed COD December 2028
190 MW
Capacity
1
Components
Battery
1y 6m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 3m
Pre-Study0%
Queue EntrySep 4, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
NY
County
Albany
Region
NYISO
Developer
BGTF US Development Holdings LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Marcy to New Scotland 345 kV line 18
Data Source
LBNL