Rutland Center Solar
BetaActiveSolarNYISOLBNL
75 MW generation in Jefferson, NY · In queue since August 2024 · Proposed COD May 2030
75 MW
Capacity
1
Components
Solar
1y 7m
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
5y 9m
Pre-Study0%
Queue EntryAug 30, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-05-01
Project Details
State
NY
County
Jefferson
Region
NYISO
Developer
Rutland Center Solar 1, LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Staplin Creek Station 115 kV
Data Source
LBNL