Falls Park Energy Storage
BetaActiveBatteryNYISOLBNL
100 MW storage in Columbia, NY · In queue since August 2024 · Proposed COD June 2030
100 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
5y 10m
Pre-Study0%
Queue EntryAug 29, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-06-01
Project Details
State
NY
County
Columbia
Region
NYISO
Developer
Falls Park Energy Storage Project, LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
FALLS PARK 115 kV
Data Source
LBNL
No news available for this project.