NY125C - Little Salmon Solar — Project Summary

Queue ID
NYISO-C24-108
Capacity
200 MW
Technology
Solar
Status
active
Location
Franklin, NY
Region
NYISO
Developer
Boralex US Development LLC
IA Status

NY125C - Little Salmon Solar

BetaActiveSolarNYISOLBNL + Live

200 MW generation in Franklin, NY · In queue since August 2024 · Proposed COD December 2028

200 MW

Capacity

1

Components

Solar

1y 7m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 4m

Pre-Study0%
Queue EntryAug 29, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

NY

County

Franklin

Region

NYISO

Developer

Boralex US Development LLC

Utility

NYPA

Entity

NYISO

Point of Interconnection

345kV Line HW1 Haverstock - WIllis

Data Source

LBNL + Live

No news available for this project.