ELP Clay Storage
BetaActiveBatteryNYISOLBNL
199 MW storage in Onondaga, NY · In queue since August 2024 · Proposed COD July 2028
199 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntryAug 28, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
NY
County
Onondaga
Region
NYISO
Developer
ELP Clay Storage LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Clay-Lighthouse Hill 115kV, Line #7
Data Source
LBNL