ELP Clay Storage — Project Summary

Queue ID
NYISO-C24-105
Capacity
199 MW
Technology
Battery
Status
active
Location
Onondaga, NY
Region
NYISO
Developer
ELP Clay Storage LLC
IA Status

ELP Clay Storage

BetaActiveBatteryNYISOLBNL

199 MW storage in Onondaga, NY · In queue since August 2024 · Proposed COD July 2028

199 MW

Capacity

1

Components

Battery

1y 7m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 11m

Pre-Study0%
Queue EntryAug 28, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-01

Project Details

State

NY

County

Onondaga

Region

NYISO

Developer

ELP Clay Storage LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Clay-Lighthouse Hill 115kV, Line #7

Data Source

LBNL