Horseblock Energy Storage — Project Summary

Queue ID
NYISO-C24-104
Capacity
100 MW
Technology
Battery
Status
active
Location
Suffolk, NY
Region
NYISO
Developer
ACE DevCo NC, LLC
IA Status

Horseblock Energy Storage

BetaActiveBatteryNYISOLBNL + Live

100 MW storage in Suffolk, NY · In queue since August 2024 · Proposed COD June 2029

100 MW

Capacity

1

Components

Battery

1y 7m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

4y 10m

Pre-Study0%
Queue EntryAug 27, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-06-01

Project Details

State

NY

County

Suffolk

Region

NYISO

Developer

ACE DevCo NC, LLC

Utility

LIPA

Entity

NYISO

Point of Interconnection

West Yaphank 69kV Substation

Data Source

LBNL + Live