Crown Point Solar
BetaActiveSolarBatteryNYISOLBNL
20 MW hybrid in Essex, NY · In queue since August 2024 · Proposed COD July 2028
20 MW
Capacity
1
Components
Solar
1y 7m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntryAug 26, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
NY
County
Essex
Region
NYISO
Developer
Crown Point Solar LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Ticonderoga to Republic 115Kv Line 2
Data Source
LBNL