Coopers Corner BESS — Project Summary

Queue ID
NYISO-C24-096
Capacity
300 MW
Technology
Battery
Status
active
Location
Sullivan, NY
Region
NYISO
Developer
ACE DevCo NC,LLC
IA Status

Coopers Corner BESS

BetaActiveBatteryNYISOLBNL

300 MW storage in Sullivan, NY · In queue since August 2024 · Proposed COD October 2029

300 MW

Capacity

1

Components

Battery

1y 7m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 2m

Pre-Study0%
Queue EntryAug 23, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-10-01

Project Details

State

NY

County

Sullivan

Region

NYISO

Developer

ACE DevCo NC,LLC

Utility

NYSEG

Entity

NYISO

Point of Interconnection

Coopers Corner 345 kV Substation

Data Source

LBNL

No news available for this project.