Scio Solar Facility
BetaActiveSolarBatteryNYISOLBNL
50 MW hybrid in Allegany, NY · In queue since August 2024 · Proposed COD September 2027
50 MW
Capacity
1
Components
Solar
1y 7m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 1m
Pre-Study0%
Queue EntryAug 20, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-01
Project Details
State
NY
County
Allegany
Region
NYISO
Developer
Quantum DPI Group
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Homer Hill to ANDOVER 115kV Line 157
Data Source
LBNL
No news available for this project.