BPP NY Somerset BESS I LLC
BetaActiveBatteryNYISOLBNL
199.5 MW storage in Niagara, NY · In queue since August 2024 · Proposed COD March 2027
199.5 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 7m
Pre-Study0%
Queue EntryAug 19, 2024
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-01
Project Details
State
NY
County
Niagara
Region
NYISO
Developer
BPP NY Somerset BESS I LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Kintigh 345kV
Data Source
LBNL