Port Morris Energy Storage — Project Summary

Queue ID
NYISO-C24-081
Capacity
130 MW
Technology
Battery
Status
active
Location
Bronx, NY
Region
NYISO
Developer
The NY Power Authority
IA Status

Port Morris Energy Storage

BetaActiveBatteryNYISOLBNL + Live

130 MW storage in Bronx, NY · In queue since August 2024 · Proposed COD December 2027

130 MW

Capacity

1

Components

Battery

1y 7m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 4m

Pre-Study0%
Queue EntryAug 8, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

NY

County

Bronx

Region

NYISO

Developer

The NY Power Authority

Utility

NYPA

Entity

NYISO

Point of Interconnection

Hell Gate Annex 138kV

Data Source

LBNL + Live

No news available for this project.